General Presentation
A virtually identical third and final phase was constructed in 1995, once again after seeking and obtaining Seaway approval. Also using three semi-Kaplan vertical units, the only significant difference was an innovative method of construction
using upstream and downstream cofferdams with poured concrete intake structures rather than the previously utilized pre-fabricated intakes.
The Côte Ste-Catherine powerhouse constitutes a striking particularity as its run-of-river production is substantially greater in winter than in summer. In fact, the head is higher when navigation is interrupted during freeze-up due
to the Seaway lowering the downstream tailrace water level.
 |
 |
|
Gross head : 12 m
|
|
Rated flow : 54 m3/s
|
|
3 Kaplan turbines : 1 600 kW
|
|
Runner diameter : 1800 mm
|
|
Capacity : 4 800 kW
|
|
Annual production : 37 350 000 kWh
|
|
|
|
Duration of construction : 9 months
|
|
Commissioning : December 1995
|
| Total investment : 10 million dollars |
|
 |
 |
Note: The Côte Ste-Catherine III hydroelectric facility is not the property of
Hydromega services inc anymore.
< Return to our projects
list
|